Shaffer v. Debbas

California Court of Appeal · D012858 · 1993-06-14 · Published · 17 Cal. App. 4th 33 · 21 Cal. Rptr. 2d 110 · 93 Cal. Daily Op. Serv. 5350 · 93 Daily Journal DAR 9024 · 1993 Cal. App. LEXIS 721

CHARLES G. SHAFFER Et Al., Plaintiffs, Respondents, and Cross-Appellants, v. NICHOLAS F. DEBBAS Et Al., Defendants, Appellants and Cross-Respondents

Area
civil
Panel
Howard B. Wiener (author)

Analysis

A model's reading — qwen3.8-27b, prompt v1, 2026-10-13T07:31Z · confidence high

The trial court entered judgment for the Shaffers based on negligence and breach of warranty, excluding evidence of collateral source insurance payments and refusing to reduce the property damage award for mitigation or comparative negligence. On appeal, the court modified the judgment to reduce the property damage award by 25% for failure to mitigate, added Franton, Inc. and T-Bear, Inc. as judgment debtors, and affirmed the exclusion of collateral source evidence and the tolling of the statute of limitations for emotional distress claims.

Ruling reviewedStandardThe courtThe model
Exclusion of evidence of collateral source payments (St. Paul insurance settlement)
“We accordingly conclude the trial court correctly prohibited defendants from introducing evidence of the Shaffers’ receipt of insurance payments from St. Paul.”
de novocorrectagree with court
The court correctly applied the collateral source rule, which California Supreme Court precedent (Helfend, Anheuser-Busch) extends to property damage, not just personal injury. The insurer waived subrogation, so no double recovery occurred, and the rule prevents a windfall to the tortfeasor.
Refusal to reduce property damage award for failure to mitigate damages
“The court was obligated to give effect to the jury’s finding and reduce this aspect of the award to $97,500.”
de novoerroragree with court
The trial court erred by failing to apply the jury's special verdict finding that 25% of the property damage could have been avoided. The appellate court correctly modified the judgment to reflect this reduction, as plaintiffs are bound by the plain language of the verdict when they fail to request more specific findings.
Refusal to reduce property damage award for comparative negligence
“We likewise reject defendants’ argument that an additional 5 percent must be deducted to give effect to the jury’s comparative negligence calculations.”
de novocorrectagree with court
The court correctly rejected the additional reduction because the special verdicts were ambiguous regarding duplicative findings and because comparative negligence is not a defense to a breach of express warranty claim, which was the prevailing theory for the greater amount of damages.
Denial of statute of limitations defense for emotional distress claims
“the jury could reasonably find that defendants were estopped to assert a limitations defense and the Shaffers were entitled all damages they suffered as a result of defendants’ conduct.”
substantial evidencecorrectagree with court
The court correctly held that the jury's finding of estoppel was supported by substantial evidence. Defendants' promises to repair the property damage reasonably induced the plaintiffs to delay filing suit for personal injury, preventing them from jeopardizing the repair process, which is a permissible application of equitable estoppel to toll the statute of limitations.
Failure to add Franton, Inc. and T-Bear, Inc. as judgment debtors
“Accordingly, the judgment, to the extent it makes an award for property damage, will be modified to add Franton, Inc., and T-Bear, Inc., as judgment debtors.”
de novoerroragree with court
The trial court erred by not adding the corporate entities as judgment debtors. The jury found a breach of warranty by the joint venture, and under settled commercial law, joint venturers and general partners of a partnership are jointly and severally liable for the venture's obligations.
Measure of damages based on cost of repair rather than diminution in value
“We see no basis to depart from the general rule on the facts of this case.”
de novocorrectagree with court
The court correctly applied the general rule that damages are measured by the lesser of cost of repair or diminution in value. The exception allowing cost of repair to exceed diminution in value (Omdotff) applies when the plaintiff has a personal reason to keep the property, which is not the case here where the plaintiffs sold the home.

Authorities

  • relied: Helfend v. Southern Cal. Rapid Transit Dist. (1970) 2 Cal.3d 1 — Collateral source rule prevents deduction of independent insurance payments from tortfeasor damages.
  • relied: Anheuser-Busch, Inc. v. Starley (1946) 28 Cal.2d 347 — Collateral source rule expressly includes property damage.
  • relied: Philip Chang & Sons Associates v. La Casa Novato (1986) 177 Cal.App.3d 159 — Property damage awards are not reduced by payments from independent sources.
  • relied: Brandon & Tibbs v. George Kevorkian Accountancy Corp. (1990) 226 Cal.App.3d 442 — Plaintiff has a duty to mitigate damages in contract cases.
  • relied: Green v. Smith (1968) 261 Cal.App.2d 392 — Plaintiff has a duty to mitigate damages in tort cases.
  • relied: Estate of Pieper (1964) 224 Cal.App.2d 670 — Estoppel to invoke statute of limitations requires conduct inducing belated filing; bad faith not required.
  • relied: Industrial Indemn. Co. v. Ind. Acc. Com. (1953) 115 Cal.App.2d 684 — Defendant's conduct inducing plaintiff to refrain from legal proceedings is sufficient for estoppel.
  • relied: County of Santa Clara v. Vargas (1977) 71 Cal.App.3d 510 — Whether estoppel exists is a question of fact.
  • relied: Holmes v. David H. Bricker, Inc. (1969) 70 Cal.2d 786 — Property damage and personal injury claims have separate statutes of limitation.
  • relied: Carruth v. Fritch (1950) 36 Cal.2d 426 — Defendant's conduct inducing belief of full compensation without litigation estops them from invoking limitations defense.
  • relied: Smalley v. Baker (1968) 262 Cal.App.2d 824 — Joint venturers are liable for the obligations of the joint venture.
  • relied: Mozzetti v. City of Brisbane (1977) 67 Cal.App.3d 565 — General rule for property damage is the lesser of cost of repair or diminution in value.
  • relied: Omdotff v. Christiana Community Builders (1990) 217 Cal.App.3d 683 — Cost of repair may exceed diminution in value if plaintiff has a legitimate personal reason to keep the property.
  • relied: Heninger v. Dunn (1980) 101 Cal.App.3d 858 — Supports the 'personal reason' exception to the lesser measure rule for property damage.

The appellate opinion: sound — The opinion is sound because it correctly applies established California law regarding the collateral source rule, duty to mitigate, and joint venture liability. It also provides a logical and policy-based justification for extending equitable estoppel to toll the statute of limitations for personal injury claims when based on promises to repair property damage.

How this analysis was made · dispute it

A model's reading — claude-fable-5-1, prompt v1, 2026-10-13T04:32Z · confidence medium

After a jury trial on negligence and breach of warranty claims arising from construction of a $1.3 million custom home, the trial court entered judgment for the Shaffers for $204,000 in property damage plus emotional distress damages, costs, and $241,900 in attorney fees against certain builder-defendants, excluded evidence of the Shaffers' insurance settlement, declined to reduce the award for the jury's mitigation and comparative negligence findings, and omitted joint venturer Franton, Inc. and general partner T-Bear, Inc. as judgment debtors. The Court of Appeal modified the judgment by reducing property damage to $171,500 (applying the 25 percent mitigation finding to the $130,000 cost-of-repair component) and adding Franton and T-Bear as judgment debtors, affirmed as modified, and remanded solely to calculate costs due Sillman/Wyman, Strang, and Semmo.

Ruling reviewedStandardThe courtThe model
Exclusion of evidence of the St. Paul insurance settlement offered as an offset to property damages (collateral source rule applies to property damage)
“We accordingly conclude the trial court correctly prohibited defendants from introducing evidence of the Shaffers’ receipt of insurance payments from St. Paul.”
de novocorrectagree with court
The court correctly applied binding Supreme Court authority (Helfend, Hrnjak, Anheuser-Busch) stating the collateral source rule without limitation to personal injury, and Philip Chang expressly applies it to property damage. Defendants' proposed limitation finds no support in the authorities, and the court's point about subrogation shows the rule operated as intended.
Refusal to reduce the $130,000 cost-of-repair component by the jury's 25 percent failure-to-mitigate finding
“The court was obligated to give effect to the jury’s finding and reduce this aspect of the award to $97,500.”
de novoerror (law misapplied)agree with court
The jury expressly found 25 percent of the property damage to the house was avoidable; the duty to mitigate applies to both contract and tort damages (Brandon & Tibbs; Green v. Smith). The Shaffers' argument that the finding applied only to diminution in value fails because the special verdict did not so limit it and they did not request more specific findings, so the plain language of the verdict controls.
Refusal to apply the 25 percent mitigation reduction to the furniture damage ($44,000) and alternate living expense ($30,000) components
“The special verdict provides no basis for concluding that any portion of the furniture damage or additional living expense was avoidable.”
de novocorrectagree with court
The jury's finding was limited to damage to the house; nothing in the verdict supports extending it to furniture or living expenses. Reading the verdict by its plain terms is consistent with the court's treatment of the Shaffers' parallel argument.
Refusal to further reduce the property damage award by the jury's 5 percent comparative negligence finding
“In any event, we are persuaded that comparative negligence is not a defense to a breach of express warranty action.”
de novocorrectunsure
The court's primary ground—that the 5 percent figure may duplicate the 25 percent mitigation finding and that the warranty theory independently supports the larger amount—is defensible. However, the proposition that comparative negligence is no defense to express warranty rests only on a Colorado case and a treatise, without engaging California authority such as Daly v. General Motors, which extended comparative fault to strict products liability; the question under California law is not settled by the authorities cited.
Denial of statute of limitations defense to the emotional distress claims based on the jury's estoppel finding
“the jury could reasonably find that defendants were estopped to assert a limitations defense and the Shaffers were entitled all damages they suffered as a result of defendants’ conduct.”
substantial evidencecorrectagree with court
Estoppel to assert the statute is a question of fact (Pieper; Vargas), bad faith is unnecessary, and Carruth v. Fritch supports estoppel where defendant's promises of compensation without litigation induced delay. Extending reliance on promises to repair property damage to the related personal injury claim is a reasonable, if novel, application that fits the policy of discouraging precipitous litigation.
Denial of builder-defendants' post-offer costs under Code of Civil Procedure section 998 ($350,001 joint offer)
“Allowing for the deduction for failure to mitigate damages as we have explained, the total judgment, including property damage ($171,500), personal injury ($33,866.01) and “pre-998” offer attorney fees ($153,914.47), still exceeds defendants’ section 998 offer.”
de novocorrectagree with court
Comparing the 998 offer with the judgment inclusive of pre-offer attorney fees recoverable under the contract is consistent with the established approach of adding pre-offer costs to the verdict. Since the adjusted judgment still exceeds $350,001, the builder-defendants did not obtain a more favorable result.
Failure to award costs to prevailing defendants Sillman/Wyman, Strang (post-998 offer costs), and Semmo
“Defendant Sillman/Wyman is entitled to costs as a prevailing party.”
de novoerror (law misapplied)agree with court
Code of Civil Procedure section 1032(b) entitles a prevailing party to costs as of right, and the Shaffers did not contest Strang's section 998 entitlement; Semmo's entitlement properly depends on the unresolved alter ego motion. Remand for calculation is the appropriate disposition.
Refusal to include Franton, Inc. and T-Bear, Inc. as judgment debtors on the property damage award
“Accordingly, the judgment, to the extent it makes an award for property damage, will be modified to add Franton, Inc., and T-Bear, Inc., as judgment debtors.”
de novoerror (law misapplied)agree with court
The jury found the joint venture breached the warranty and awarded $130,000 on that basis; joint venturers are liable for joint venture obligations (Smalley v. Baker) and general partners are jointly and severally liable for partnership obligations (Corp. Code §§ 15013, 15015). The court reasonably read the negligence special verdict as not negating vicarious liability.
Entry of judgment on the lesser cost-of-repair measure ($130,000) rather than diminution in value ($585,000)
“We see no basis to depart from the general rule on the facts of this case.”
de novocorrectagree with court
The general rule awards the lesser of cost of repair or diminution in value (Mozzetti); Orndorff and Heninger permit the greater cost-of-repair measure only to protect a plaintiff's personal reasons for keeping property, a rationale inapplicable where the plaintiff chose to sell. The court's distinction is coherent.
Rejection of the Shaffers' request for a separate measure of damages on negligent misrepresentation (footnote 3)
“Having failed to object to the special verdict forms or otherwise raise this issue in the trial court, the Shaffers are precluded from making a complaint here.”
de novocorrectagree with court
Forfeiture for failing to object to special verdict forms or raise the issue below is a standard application of waiver principles; the opinion gives no indication the issue was preserved.

Authorities

  • relied: Helfend v. Southern Cal. Rapid Transit Dist. (1970) 2 Cal.3d 1 — Collateral source rule: payments from a source wholly independent of the tortfeasor are not deducted from damages; policy encourages insurance for personal injuries and other eventualities.
  • relied: Hrnjak v. Graymar, Inc. (1971) 4 Cal.3d 725 — Reaffirms the collateral source rule and exclusion of collateral source evidence.
  • relied: Anheuser-Busch, Inc. v. Starley (1946) 28 Cal.2d 347 — Collateral source rule applies to property damage claims.
  • relied: Philip Chang & Sons Associates v. La Casa Novato (1986) 177 Cal.App.3d 159 — Property damage recovery is not reduced by payments from a source independent of the wrongdoer.
  • relied: Auto Equity Sales, Inc. v. Superior Court (1962) 57 Cal.2d 450 — Courts of Appeal are bound by Supreme Court decisions.
  • relied: Brandon & Tibbs v. George Kevorkian Accountancy Corp. (1990) 226 Cal.App.3d 442 — A party injured by breach of contract must take reasonable steps to mitigate damages and cannot recover avoidable losses.
  • relied: Green v. Smith (1968) 261 Cal.App.2d 392 — Tort plaintiff has a duty to mitigate damages.
  • relied: Estate of Pieper (1964) 224 Cal.App.2d 670 — Estoppel to assert the statute of limitations does not require bad faith and is a question of fact.
  • relied: Industrial Indemn. Co. v. Ind. Acc. Com. (1953) 115 Cal.App.2d 684 — It suffices that defendant's conduct in fact induced plaintiff to refrain from suing.
  • relied: County of Santa Clara v. Vargas (1977) 71 Cal.App.3d 510 — Existence of estoppel to plead limitations is a question of fact.
  • relied: Holmes v. David H. Bricker, Inc. (1969) 70 Cal.2d 786 — A single wrongful act causing property damage and personal injury gives rise to separate causes of action with separate limitations periods.
  • relied: Carruth v. Fritch (1950) 36 Cal.2d 426 — Defendant who induces plaintiff to delay suit by promising compensation without litigation is estopped to assert the statute of limitations.
  • relied: Smalley v. Baker (1968) 262 Cal.App.2d 824 — Joint venturers are liable for obligations of the joint venture.
  • relied: Weiner v. Fleischman (1991) 54 Cal.3d 476 — Disapproved Smalley v. Baker on other grounds (standard of proof for joint venture existence).
  • relied: Mozzetti v. City of Brisbane (1977) 67 Cal.App.3d 565 — Property damage is generally measured by the lesser of cost of repair or diminution in value.
  • relied: Orndorff v. Christiana Community Builders (1990) 217 Cal.App.3d 683 — Cost of repair exceeding diminution in value may be awarded where plaintiff has a legitimate personal reason to keep the property.
  • relied: Heninger v. Dunn (1980) 101 Cal.App.3d 858 — Personal-reason exception to the lesser-measure rule for property damage.
  • missed: Daly v. General Motors Corp. (1978) 20 Cal.3d 725 — Comparative fault principles apply to strict products liability actions; relevant to whether comparative negligence can reduce recovery on a warranty theory, which the court resolved on out-of-state authority alone.

The appellate opinion: sound with gaps — The opinion correctly applies binding collateral source, mitigation, estoppel, partnership, and measure-of-damages authority, and its reading of the special verdicts is careful and consistent across the parties' competing arguments. It is thinner on the comparative negligence point, resting a California-law proposition on a Colorado decision and a treatise without addressing California comparative fault authority, though the alternative ground (duplication and the warranty theory supporting the full amount) makes the result defensible.

How this analysis was made · dispute it

Opinion — Wiener

Opinion

WIENER, Acting P. J.

Both plaintiff-homeowners and defendant-contractors appeal from a judgment in favor of plaintiffs Charles and Betty Shaffer for damages based on theories of negligence and breach of warranty arising from the construction of a custom home. A detailed review of the lengthy record in this case is unnecessary for the purposes of the issues raised in this appeal. It is sufficient to note that the Shaffers contracted with the Avenida Alondra joint venture to build a custom house for them at a purchase price of $1.3 million. The house was warranted to be free from defects in materials and workmanship for one year.

The Shaffers took possession in August 1983 and almost immediately began experiencing a variety of problems owing largely to drainage defects and improper installation of the heating and air conditioning system. The defects were not repaired despite repeated promises by the builders to do so, and the condition of the house deteriorated. In 1987 the Shaffers moved from the house because of its deteriorating condition and in December 1988 they sold the property for $950,000.

This lawsuit was filed in October 1986. Named as defendants were the two joint venturers, Pieri-Debbas Enterprises (a partnership) and Franton, Inc. Also named were Franton’s sole shareholder (Frank Semmo), the two corporate general partners of Pieri-Debbas (Debbas Construction, Inc., and T-Bear, Inc.) and the sole shareholders of Debbas Construction and T-Bear *39 (Nicholas Debbas and James Fieri, respectively). Debbas, Fieri and Semmo were alleged to be alter egos of their individual corporations. These defendants are collectively referred to as the builder-defendants. In addition, the Shaffers also sued the project architects (Sillman/Wyman & Associates) and the heating and air conditioning subcontractors (Strang Heating and Air Conditioning, Inc.). 1 All defendants were jointly represented at trial.

The jury found in favor of the Shaffers pursuant to a complex set of special verdict forms. The original judgment awarded the Shaffers $204,000 for property damage, of which $3,000 was to be paid by Strang. The special verdicts broke the $204,000 down into three components: (1) $130,000 represented the reasonable cost of repairing the house while the Shaffers lived there; (2) $44,000 represented damage to furniture in the house; and (3) $30,000 represented compensation for expenses the Shaffers incurred in arranging for alternate living quarters. Charles Shaffer was awarded $1,782.42 damages for emotional distress, while Betty Shaffer was awarded $32,083.59 on a similar theory. The judgment provided that the Shaffers would recover nothing from defendants Semmo, Franton, Inc. and Sillman/ Wyman. Later amended judgments included attorney fees (based on a fee provision in the construction contract) and costs. The final amended judgment provided that the Shaffers’ award for property damage and emotional distress (other than the $3,000 assessed against Strang) was recoverable against Debbas and Fieri individually, the Pieri-Debbas partnership and Debbas Construction. Costs of $38,073.73 were assessed against the same defendants. Attorney fees of $241,900 were also assessed against the same defendants and, in addition, T-Bear, Inc.

Discussion

I. Defendants’ Appeal

A. Evidence of Collateral Source Payments

In 1987, the Shaffers filed an action against their homeowners’ insurer, St. Paul Fire & Marine Insurance Company, to recover for the same property damage at issue in this case. A jury returned a verdict in favor of the Shaffers, awarding $753,000 in damages. Following the judgment, St. Paul and the Shaffers agreed to settle their dispute. In exchange for a discount in excess of $250,000 on the judgment, St. Paul waived any rights of subrogation it had in this action, leaving the Shaffers to prosecute without intervention by St. Paul.

*40 Defendants unsuccessfully sought to introduce evidence of the St. Paul settlement as an offset against any property damage judgment in this case. They now contend that the exclusion of the evidence was error. Responding to the Shaffers’ argument that the collateral source rule (see Helfend v. Southern Cal. Rapid Transit Dist. (1970) 2 Cal.3d 1, 6 [84 Cal.Rptr. 173, 465 P.2d 61, 77 A.L.R.3d 398]) precludes such an offset, defendants argue that the rule “applies only to personal injury claims, where a company providing medical insurance for which the injured person has paid is not in a position to pursue a subrogation claim.”

The collateral source rule provides that where “an injured party receives some compensation for his injuries from a source wholly independent of the tortfeasor, such payment should not be deducted from the damages which the plaintiff would otherwise collect from the tortfeasor.” (.Helfend, supra, 2 Cal.3d at p. 6.) The rule has been repeatedly reaffirmed by the California Supreme Court as “a policy judgment in favor of encouraging citizens to purchase and maintain insurance for personal injuries and other eventualities.” (Id. at p. 10; see also Hmjak v. Graymar, Inc. (1971) 4 Cal.3d 725, 729-730 [94 Cal.Rptr. 623, 484 P.2d 599, 47 A.L.R.3d 224].) We are, of course, bound by the Supreme Court’s pronouncements. (Auto Equity Sales, Inc. v. Superior Court (1962) 57 Cal.2d 450, 455 [20 Cal.Rptr. 321, 369 P.2d 937].) As to defendants’ suggestion that the rule can somehow be limited to cases of personal injury involving medical insurance payments, the Supreme Court’s statement of the rule suggests no such limitation and its reference to “other eventualities” (quoted above) is inconsistent with the proffered interpretation. Indeed, the Supreme Court has expressly stated the rule so as to include property damage. (Anheuser-Busch, Inc. v. Starley (1946) 28 Cal.2d 347, 349 [170 P.2d 448, 166 A.L.R. 198].) As the court summarized in Philip Chang & Sons Associates v. La Casa Novato (1986) 177 Cal.App.3d 159, 166 [222 Cal.Rptr. 800], “The rule has been oft repeated to provide that where a person suffers property damage, the amount of damages shall not be reduced by the receipt by him of payment for his loss from a source wholly independent of the person who caused the injury.” The contrary rule suggested by defendants would result in a substantial windfall to those parties principally responsible for a plaintiffs property damage.

Moreover, the rule worked as it should have in this case. As Helfend explains, the feared “double recovery” by a plaintiff seldom occurs because the paying insurer is subrogated to the rights of the insured as against the defendants who caused the injury. (See Helfend, supra, 2 Cal.3d at pp. 10-11.) Here, St. Paul was subject to a $753,000 judgment in favor of the Shaffers. In exchange for a $250,000 discount, it was apparently willing to *41 wager that the Shaffers would recover no more than that amount as against defendants. As it turns out, the total award for property damage less alternate living expenses was $174,000. 2 In effect, St. Paul obtained more than it would have had it paid the judgment and pursued its subrogation rights.

We accordingly conclude the trial court correctly prohibited defendants from introducing evidence of the Shaffers’ receipt of insurance payments from St. Paul.

B. Reduction of Property Damage Award Due to Failure to Mitigate Damages

By special verdict the jury found that 25 percent of “the total amount of property damage to the house . . . could have been avoided by plaintiffs’ reasonable care and diligence to avoid loss and minimize the damages.” Also, in a separate special verdict on negligence, the jury found that 5 percent of “the total negligence which was the legal cause of the plaintiffs’ damage” was attributable to the “contributory negligence” of the Shaffers. The trial court refused to reduce the property damage award by any amount attributable either to a failure to mitigate damages or the Shaffers’ comparative negligence.

We agree with defendants that the component of the damage award represented by the reasonable cost of repairing the property—$130,000— must be reduced by the 25 percent “mitigation of damage” figure determined by the jury. A plaintiff who suffers damage as a result of either a breach of contract or a tort has a duty to take reasonable steps to mitigate those damages and will not be able to recover for any losses which could have been thus avoided. (E.g., Brandon & Tibbs v. George Kevorkian Accountancy Corp. (1990) 226 Cal.App.3d 442, 460 [277 Cal.Rptr. 40] [contract]; Green v. Smith (1968) 261 Cal.App.2d 392, 396 [67 Cal.Rptr. 796] [tort].) Here the jury determined that 25 percent of the “property damage to the house” could have been avoided. That damage was measured by the cost of repair, i.e., $130,000. The court was obligated to give effect to the jury’s finding and reduce this aspect of the award to $97,500.

The Shaffers argue the jury must have intended the 25 percent reduction to apply only if the property damage was measured by the diminution in value of the residence. (See post, pp. 46-47.) In support of this assertion they point to evidence indicating the Shaffers sold the house at a below-market price. While this may be what the jury focused on, the special verdicts, unfortunately, did not separate the mitigation-of-damages finding as it applied to the *42 different measures of damages. Moreover, there was evidence which would support a finding that the cost of repair was higher than it should have been due to the Shaffers’ landscaping work, overwatering and installation of solar panels. Having failed to request more specific findings as to the mitigation-of-damage issue, the Shaffers are bound by the plain language of the verdict.

We reject defendants’ additional contention that the 25 percent reduction should be applied as well to those portions of the property damage award representing damage to furniture ($44,000) and additional living expenses ($30,000). The jury only found that some of the “damage to the house” could have been mitigated. The special verdict provides no basis for concluding that any portion of the furniture damage or additional living expense was avoidable.

We likewise reject defendants’ argument that an additional 5 percent must be deducted to give effect to the jury’s comparative negligence calculations. The special verdicts are far from clear that the collective 5 percent comparative negligence figure (IV2 percent for both Charles and Betty) is not at least to some extent duplicative of the 25 percent mitigation-of-damages reduction. In any event, we are persuaded that comparative negligence is not a defense to a breach of express warranty action. (See, e.g., Hensley v. Sherman Car Wash Equipment Company (1974) 33 ColoApp. 279 [520 P.2d 146, 148]; 2 Shapo, The Law of Products Liability (2d ed. 1990) 120.01[15], p. 20-15.) Assuming the negligence special verdict should result in an additional 5 percent reduction as to that theory, the judgment would nonetheless reflect the greater amount attributable to the breach of warranty theory.

C. Statute of Limitations: Emotional Distress

There was abundant evidence indicating that the builder-defendants, particularly Debbas, continued to make promises to the Shaffers as late as 1987 that the problems with the house would be fixed. Defendants concede this evidence was sufficient to toll the statute of limitations with respect to the property damage claim. (See, e.g., Senior Housing v. Nakawatase, etal. (1989) 192 Hl.App.3d 766 [139 Ill.Dec. 878, 549 N.E.2d 604].) They assert, however, that the Shaffers’ respective claims for emotional distress were barred by the applicable one-year statute of limitations. (See Code Civ. Proc., § 340, subd. (3).)

The jury determined that Charles and Betty each became aware of his or her emotional injury and its cause in June and August of 1984, respectively. It found in addition that defendants made no promises to the Shaffers that *43 their emotional distress would be compensated. Nonetheless, it also concluded that conduct by defendants induced the Shaffers to delay filing their emotional distress claims. Defendants argue that the evidence showing defendants’ continuing promises to repair the house is insufficient to support this latter finding.

A defendant will be estopped to invoke the statute of limitations where there has been “some conduct by the defendant, relied on by the plaintiff, which induces the belated filing of the action.” (3 Witkin, Cal. Procedure (3d ed. 1985) Actions, § 523, p. 550.) It is not necessary that the defendant acted in bad faith or intended to mislead the plaintiff. (Estate of Pieper (1964) 224 Cal.App.2d 670, 690 [37 Cal.Rptr. 46]; Industrial Indemn. Co. v. Ind. Acc. Com. (1953) 115 Cal.App.2d 684, 690 [252 P.2d 649].) It is sufficient that the defendant’s conduct in fact induced the plaintiff to refrain from instituting legal proceedings. (Industrial lndem., supra, 115 Cal.App.2d at p. 690.) “[Wjhether an estoppel exists—whether the acts, representations or conduct lulled a party into a sense of security preventing him from instituting proceedings before the running of the statute, and whether the party relied thereon to his prejudice—is a question of fact and not of law.” (.Pieper, supra, 224 Cal.App.2d at pp. 690-691; County of Santa Clara v. Vargas (1977) 71 Cal.App.3d 510, 524 [139 Cal.Rptr. 537].)

The estoppel issue in this case arises in a unique context. Defendants’ wrongful conduct has given rise to separate causes of action for property damage and personal injury with separate statutes of limitation. (See Holmes v. David H. Bricker, Inc. (1969) 70 Cal.2d 786, 789 [76 Cal.Rptr. 431, 452 P.2d 647].) Where the plaintiffs reasonably rely on defendants’ promise to repair the property damage without a lawsuit, is a jury permitted to find that plaintiffs’ decision to delay filing a personal injury lawsuit was also reasonable? We conclude such a finding is permissible on the facts of this case.

Where a potential defendant has promised to remedy a portion of the damages suffered by the plaintiff, it would be unreasonable to expect the plaintiff to jeopardize the possibility of repair by filing a lawsuit as to items of damage not covered by the defendant’s promise. This is particularly true where, as here, the defendant’s promise relates to a substantial aspect of the dispute. Certainly the effect of a contrary rule would be to foster the precipitous filing of actions and reduce the possibility of settlement without litigation, outcomes hardly in the best interests of the judicial system or the public at large.

In addition, it may be that at the point in time where the one-year personal injury statute of limitations expired, plaintiffs were willing to waive any *44 claim of entitlement to personal injury compensation in exchange for defendants’ promise to repair the property damage. When defendants failed to fulfill that promise, it hardly seems fair to enforce an implied waiver of the personal injury claim. A somewhat analogous issue arose in Carruth v. Fritch (1950) 36 Cal.2d 426 [224 P.2d 702, 24 A.L.R.2d 1403] where plaintiff Carruth, a passenger in an automobile owned by the defendant Fritch and driven by his son, suffered injuries in a traffic accident. Before any suit was filed, in exchange for Carruth’s release Fritch agreed to pay plaintiff $2,000 for already incurred medical expenses and to cover any future medical expenses related to the injury. Fritch also agreed to compensate plaintiff for lost wages.

Carruth contacted Fritch after she was forced to reenter the hospital for treatment but Fritch disclaimed any obligation to her. She then filed suit seeking to recover for all her injuries, including pain and suffering damages, less the $2,000 already paid. The court began by noting that “[a] timely action for personal injuries may be maintained notwithstanding a release procured by fraud” (36 Cal.2d at p. 431) and went on to explain that the issue in the case was whether the action filed more than a year after the injury occurred was barred by the statute of limitations or whether Fritch’s conduct in obtaining the release estopped him from invoking a limitations defense. (Id. at p. 432.) It held that Carruth justifiably “refrained from bringing an action until after the period of limitation, because she was induced to believe she would be fully compensated for all medical expenses and loss of salary without litigation.” (Id. at p. 434.) Accordingly, she was entitled to prosecute her claim for personal injuries.

Similarly here, the Shaffers delayed bringing an action in reliance on defendants’ promises that the property damage would be repaired. Where defendants failed to fulfill that promise—indeed where the evidence suggests defendants never intended to perform—the jury could reasonably find that defendants were estopped to assert a limitations defense and the Shaffers were entitled all damages they suffered as a result of defendants’ conduct.

D. Defendants’ Entitlement to Costs and Attorney Fees

On a variety of theories defendants claim entitlement to attorney fees and costs. In view of the conclusions we reach on the substantive issues in this case, we dispose of these contentions in a summary fashion as follows:

(1) In view of our conclusion that Franton, Inc., and T-Bear, Inc., were properly added as judgment debtors (see post, p. 46), we reject their argument that they were entitled to fees and costs as prevailing defendants.

*45 (2) Our conclusions with respect to the proper calculation of property damage (ante, pp. 41-42) necessarily imply our rejection of the builder-defendants’ argument they are entitled to costs incurred after December 28, 1989, the date of their joint offer pursuant to Code of Civil Procedure section 998 in the amount of $350,001. Allowing for the deduction for failure to mitigate damages as we have explained, the total judgment, including property damage ($171,500), personal injury ($33,866.01) and “pre-998” offer attorney fees ($153,914.47), still exceeds defendants’ section 998 offer.

(3) Defendant Sillman/Wyman is entitled to costs as a prevailing party. (See Code Civ. Proc., § 1032, subd. (b).)

(4) The Shaffers do not appear to contest defendant Strang’s claim of entitlement to costs incurred after April 11, 1989, the date of its $25,000 offer pursuant to Code of Civil Procedure section 998.

(5) The Shaffers filed a postjudgment motion to have defendant Semmo declared an alter ego of Franton, Inc., which was never ruled on because it was pending at the time the notice of appeal was filed. Semmo is entitled to fees and costs as a prevailing defendant unless, on remand, the Shaffers renew and the trial court grants the alter ego motion.

In light of our conclusions, a remand is necessary for the limited .purpose of allowing the trial court to determine the amount of costs due defendants Sillman/Wyman, Strang, and Semmo (if any).

II. Plaintiffs’ Cross-appeal

A. Addition of Judgment Debtors

Relying on settled principles of law as to the liability of joint venturers and general partners, the Shaffers argue the trial court erred in failing to include Franton, Inc., and T-Bear, Inc., as judgment debtors. Defendants respond that the jury never found that the Avenida Alondra joint venture was liable but only that certain constituent entities bore responsibility for the Shaffers’ damages. They assert that the fact the jury found the warranty was breached is not dispositive because the jury could have found the breach did not cause the Shaffers’ losses. Defendants attempt to support this argument by reference to the special verdict form on negligence which, they contend, indicates the jury found that T-Bear and Franton did not cause any damage to the Shaffers.

We think defendants misread the special verdict forms. As a second question following the finding of a breach of warranty, the jury was asked to *46 specify the defects in the house which existed within one year of the completion of the house and the damages attributable to each. The total damage figure, $130,000, matches the cost-of-repair damage figure specified by the jury on the following page where it calculated the property damage. While file special verdicts might have been more artfully drafted, we think it clear the jury found a breach of warranty by the Avenida Alondra joint venture and awarded damages on that basis.

The negligence special verdict does not suggest a different conclusion. The jury was given a list of defendants and asked to determine which were negligent. Defendants Semmo, Franton, T-Bear and Sillman/Wyman were found to be not negligent. The next question asked, “As to each defendant that you answered “Yes” in response to Question No. 1, was such negligence legal cause of damage to the plaintiff?” Although the question did not call for a response as to the four defendants who were found not negligent, the jury nonetheless answered “No.” Contrary to defendants’ argument, these responses do not indicate a factual finding that Franton and T-Bear were not a legal cause of the Shaffers’ damages based on vicarious liability theories owing to their status as a joint venturer or general partner of a joint venturer, and in any event the negligence special verdict cannot detract from the jury’s earlier finding that the Shaffers suffered damage as a result of the joint venture’s breach of warranty.

The jury having found that the joint venture breached the Shaffers’ warranty, settled principles of commercial law require that both joint venturers (Pieri-Debbas Enterprises and Franton) are liable. (See Smalley v. Baker (1968) 262 Cal.App.2d 824, 837 [69 Cal.Rptr. 521], disapproved on other grounds in Weiner v. Fleischman (1991) 54 Cal.3d 476, 485-486 [286 Cal.Rptr. 40, 816 P.2d 892].) Because Pieri-Debbas was a partnership, its general partners (Debbas Construction, Inc., and T-Bear) are jointly and severally liable for its obligations. (See Corp. Code, §§ 15013, 15015.) Accordingly, the judgment, to the extent it makes an award for property damage, will be modified to add Franton, Inc., and T-Bear, Inc., as judgment debtors.

B. Measure of Damages

The jury calculated the damage to the Shaffers’ residence using the alternative theories of cost of repair and diminution in value. Because diminution in value ($585,000) greatly exceeded the cost of repair ($130,000), judgment was entered based on the lesser cost-of-repair figure in accord with the general rule. (See, e.g., Mozzetti v. City of Brisbane (1977) 67 Cal.App.3d 565, 576 [136 Cal.Rptr. 751].) Relying by analogy on this *47 court’s decision in Omdotff v. Christiana Community Builders (1990) 217 Cal.App.3d 683 [266 CalJRptr. 193], the Shaffers argue their actual sale of the house in a distressed condition should result in a damage award based on diminution of value, the loss they actually suffered.

In Omdotff we relied on Heninger v. Dunn (1980) 101 Cal.App.3d 858 [162 Cal.Rptr. 104] in holding that a plaintiff might be awarded the actual cost of repair even though it exceeded the diminution in value of his or her property if their was a legitimate “personal reason” why the plaintiff chose to keep the property rather than sell. We noted that a rigid application of the “lesser measure” rule would force many plaintiffs to abandon their personal residence. (217 Cal.App.3d at p. 690.)

In this “flip side” of Omdotff, awarding damages based on cost of repair will not force plaintiffs to remain on property they prefer to sell. Indeed, the prudent course for a plaintiff in such a situation would be to make the repairs and then sell the property at the inflated price. We see no basis to depart from the general rule on the facts of this case. 3

Disposition

The judgment is modified by reducing the amount awarded for property damage to $171,500 and by including defendants Franton, Inc., and T-Bear, Inc., as judgment debtors. As modified, the judgment is affirmed. The case is remanded to the superior court for the limited purpose of calculating the amount of costs due defendants Sillman/Wyman, Strang and Semmo (if any). Respondents and cross-appellants shall recover costs for this appeal.

Froehlich, J., and Nares, J., concurred.

Appellant’s petition for review by the Supreme Court was denied September 16, 1993.

1

The complaint also named the project soils engineer (San Dieguito Soils, Inc.) but it did not participate in the trial as a result of a federal bankruptcy stay.

2

Indeed, we later conclude that even this amount must be reduced to $141,500. (See post, this page.)

3

The Shaffers also suggest a different measure of damages may be appropriate as to their cause of action for negligent misrepresentation. Although it is true the jury found that certain of the defendants made negligent misrepresentations to the Shaffers which induced their purchase of the house, the verdict forms made no attempt to quantify the damages flowing from these misrepresentations other than as part of the general calculations of property damage based on cost of repair and diminution of value. Having failed to object to the special verdict forms or otherwise raise this issue in the trial court, the Shaffers are precluded from making a complaint here.