Pantone v. 100 Speedlab, LLC

District Court, S.D. California · 3:25-cv-01490 · 2025-07-11 · Unknown

Proceeding
district
Area
civil
Panel
Cynthia Ann Bashant (author)

Analysis

A model's reading — qwen3.8-27b, prompt own-v1, 2026-10-13T21:00Z · confidence high

Plaintiff filed an unopposed motion to extend the deadline for Defendants to respond to the Complaint, which had already passed. The Court granted the motion in part, ordering Defendants to respond by July 21, 2025, while warning that future requests must meet the proper legal standards.

What the court decidedThe model
Motion to Extend Time Granted in Part
“Because the interest of justice weighs heavily in favor of granting some sort of extension, the Court GRANTS IN PART Plaintiff’s Motion to extend Defendants’ deadline to respond. Defendants are ORDERED to respond to Plaintiff’s Complaint no later than July 21, 2025.”
agree with court
The court correctly identified that the standard for extending a deadline after it has passed is 'excusable neglect' under Rule 6(b)(1)(B), not 'good cause.' It applied the Pioneer factors, noting that while the reason for delay (vacation) weighed against the motion, the lack of prejudice and short delay weighed in favor. Granting the extension to preserve the right to a defense is a defensible exercise of discretion, even if the 'excusable neglect' showing was weak.

The order itself: sound — The order correctly identifies the applicable legal standard (excusable neglect vs. good cause) and cites the correct binding authorities (Rule 6(b)(1)(B), Pioneer, Ahanchian). It applies the factors logically, acknowledging the weakness of the 'reason for delay' but balancing it against the lack of prejudice and the fundamental right to defend oneself. The result is defensible and procedurally sound.

How this analysis was made · dispute it

unusual disposition

Opinion

1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 SOUTHERN DISTRICT OF CALIFORNIA 10 11 FELIPE PANTONE, Case No. 25-cv-1490-BAS-SBC 12 Plaintiff, ORDER GRANTING IN PART 13 v. MOTION FOR EXTENSION OF TIME (ECF No. 5) 14 100% SPEEDLAB, LLC; SAULE, LLC;

and DOES 1-10, 15 Defendants. 16 17 18 Plaintiff files an Unopposed Motion to Extend Time for Defendants to Respond to 19 Complaint on Defendants’ behalf. (ECF No. 5.) Defendants have not yet responded to 20 Plaintiff’s Complaint in this case although Plaintiff served Defendants on June 12, 2025. 21 (ECF Nos. 3, 4.) Accordingly, Defendants’ deadline to respond to the Complaint passed 22 on July 3, 2025. See Fed. R. Civ. P. 12(a) (requiring a response to a complaint be served 23 within twenty-one (21) days of service of the summons and complaint). 24 Plaintiff files the instant motion, arguing good cause exists for extending 25 Defendants’ deadline to respond on the grounds that “Defendants’ principal only recently 26 returned from vacation in Hawaii and thus has only recently been able to seek legal counsel 27 regarding the Complaint.” (ECF No. 5 at 2.) First—good cause is not the standard here. 28 The standard is excusable neglect. Fed. R. Civ. P. 6(b)(1)(B). When a party moves for an 1 extension once a deadline has passed, that party must show they “failed to act because of 2 excusable neglect.” Id.; see also Ahanchian v. Xenon Pictures, Inc., 624 F.3d 1253, 1261 3 (9th Cir. 2010) (laying out the four factors for determining excusable neglect as “(1) the 4 danger of prejudice to the opposing party; (2) the length of the delay and its potential impact 5 on the proceedings; (3) the reason for the delay; and (4) whether the movant acted in good 6 faith” (citing Pioneer Inv. Servs. Co. v. Brunswick Assocs. Ltd. P’ship, 507 U.S. 380, 395 7 (1993)). Second, Defendants make no such showing here. Instead, they request Plaintiff 8 make the motion on their behalf seven days after the deadline to respond has already 9 passed, citing a vacation as the cause of their tardiness. (ECF No. 5 at 2.) 10 Court deadlines are serious affairs. The Court finds it difficult to understand how 11 one person of two companies being on vacation precluded Defendants from obtaining 12 counsel and responding to the lawsuit in a timely fashion, or at least requesting an extension 13 before the deadline to respond passed. Defendants make no showing to meet the standard 14 for excusable neglect—they do not, for example, state that their principal is the only 15 employee of either or both of Defendants; that there was no way for the principal to get in 16 contact with anyone while the principal was on vacation; or that the principal, as the only 17 employee of either LLC, only learned about the lawsuit upon returning from the vacation 18 three days ago. 19 Although the third Pioneer factor, the reason for the delay, weighs heavily against 20 granting an extension, at least two other Pioneer factors counsel granting the request. 21 Plaintiff’s counsel represents Plaintiff will suffer no prejudice by the grant of an extension 22 (ECF No. 5 at 2), and the length of the delay will ultimately be no more than eighteen days. 23 Further, if the Court refused the extension, it would prevent Defendants from defending 24 themselves in this action. Because the interest of justice weighs heavily in favor of granting 25 some sort of extension, the Court GRANTS IN PART Plaintiff’s Motion to extend 26 Defendants’ deadline to respond. Defendants are ORDERED to respond to Plaintiff’s 27 Complaint no later than July 21, 2025. 28 1 DEFENDANTS ARE WARNED that any future requests to extend deadlines must 2 ||meet the required standards to make a showing to have any future extension granted. 3 IT IS SO ORDERED. 4 5 || DATED: July 11, 2025 yatta Bahar 6 Hon. Cynthia Bashant, Chief Judge 4 United States District Court 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 □□□